On Plastova Street in Lviv, the construction of a complex for the processing of household waste continues. The degree of its readiness is estimated at 65%.
It is reported by "Public. Lviv. "
According to experts, the new enterprise will be able to process all household waste generated in Lviv per year – about 250 thousand tons. It will undergo mechanical and biological processing.
The head of the LCP "Green City" Alexander Egorov says that today a fairly large amount of equipment has already been delivered for ventilation installations, for electric generator installations, a significant amount of equipment is now leaving Turkey.
Director of the Department of Economic Development Inna Svistun assured that the total cost of the plant's construction has not changed – it remained at €35 million. Of these, €15 million are loan funds, €10 million is a grant from the Bank of Reconstruction and Development, and the remaining €10 million is a contribution cities
The remaining waste, which is 15% of all processed garbage, is planned to be sent to landfills for disposal, but where exactly is not yet known.
"At the moment, such a place has not yet been determined," comments Inna Svystun.
But RDF fuel will be sold to cement factories, says Oleksandr Egorov.
"There is already a signed memorandum with the cement plant in Ivano-Frankivsk, constant negotiations are underway," he added.
In April 2023, 100% of the design and 25% of construction works for a waste processing plant in Lviv. Then the mayor of the city, Andriy Sadovy, told what the company was going to complete are planning until the end of 2023. At the beginning of July of the same year preparedness was ssh,sh%
Also, EcoPolitic told about intentions of an Austrian investor to build a waste processing plant and landfill for waste disposal on the territory of the regional landscape park "Ravske Roztochchia" in the Lviv region.