Businesses have been told how much time they have for eco-modernization under the new law No. 3855-IX

Businesses have been told how much time they have for eco-modernization under the new law No. 3855-IX shutterstock
Hanna Velyka

The period of transition to the new rules of operation will depend on the type of installation

Existing plants will have 3 years to apply plus another 1 year to obtain an integrated environmental permit (IEP), which is required by the Law of Ukraine “On Integrated Prevention and Control of Industrial Pollution”.

This was reported by the Ministry of Environmental Protection and Natural Resources of Ukraine.

The ministry reminded that the company must first determine whether the facility falls within the list of activities for which an integrated environmental permit is required by the Law.

The specific timing of the transition to an IED will depend on the “type” of installation. There are 4 possible options:

  • existing facilities that are planned to continue operating;
  • existing facilities that will be decommissioned within 10 years from the date of entry into force of the Law, and will actually receive the so-called “death permit”;
  • facilities that are put into operation for the first time;
  • facilities that are put into operation for the first time within 1 year from the date of entry into force of the Law.

The officials emphasized that the terms of integrated environmental permits for such facilities will differ during the period of martial law and after its termination or cancellation.

The Ministry of Environment also drew stakeholders' attention to the fact that the countdown will start on August 8, 2025, as this is the date when the Law of Ukraine No. 3855 “On Integrated Prevention and Control of Industrial Pollution” will come into force.

For convenience, the Ministry has provided detailed information in the form of an infographic:

t.me/mindovkillia

Source: t.me/mindovkillia.

In other words, in order to obtain an IED for a new facility, it must comply with the conclusions of the best available management practices and technologies (BAT) from the date of their entry into force.

For existing facilities, the requirement to comply with BAT is postponed for 4 years from the date of termination or lifting of martial law.

Recently, EcoPolitic informed its readers about the current degree of readiness to implement the industrial pollution reform. In particular, we talked about the bylaws and regulations that have already been adopted, as well as those that are in the final stages.

Related
There is no ideal candidate for NETS: experts’ views on the proposed draft laws
There is no ideal candidate for NETS: experts’ views on the proposed draft laws

Spoiler: the experts do not have a single clear favourite, but their list of necessary improvements turned out to be fairly unanimous

Where to report environmental offences: links and contact details
Where to report environmental offences: links and contact details

The most important thing is to document the facts of the violation and its location as thoroughly as possible, and to take photos and videos

ETS in Ukraine: a detailed analysis of all draft laws, without any unnecessary commentary
ETS in Ukraine: a detailed analysis of all draft laws, without any unnecessary commentary

Four draft laws, one carbon market and billions in future revenue: we break down who stands to gain what

Forests and mountains sacrificed for renewable energy: activists urge the Rada not to vote for Bill No. 15122
Forests and mountains sacrificed for renewable energy: activists urge the Rada not to vote for Bill No. 15122

Parliamentary lawyers agree that the implementation of the provisions of the law will have a negative impact on land containing forests, marshes, water bodies and fields