The contractor was delaying the construction of a waste-to-energy plant. Lviv terminated the contract

The contractor was delaying the construction of a waste-to-energy plant. Lviv terminated the contract Пресслужба Львівської міської ради
Maria Semenova

It is not yet known when the plant will finally begin operations. Further details will be provided at a later date

The Polish contractor Control Process S.A. systematically failed to fulfill the terms of the contract for the construction of a mechanical-biological treatment plant for solid municipal waste in Lviv. Due to the contractor’s refusal to perform certain works, its failure to allow other contractors access to the site, and other violations, the municipal enterprise “Green City” sent the contractor a notice of contract termination.

This was reported by the press service of the Lviv City Council.

All grounds for terminating the contract are documented and, according to municipal enterprise representatives, are substantial.

"Due to Control Process S.A.’s systematic failure to fulfill its obligations, as well as its failure to comply with the FIDIC engineer’s instructions and its lack of response to these comments, we have decided to terminate the agreement with this contractor," explained Oleksandr Yegorov, director of the municipal enterprise "Green City."

Unfulfilled conditions

The Lviv City Administration reported that the contractor received repeated requests to remedy the contract violations throughout 2025.

In particular, the contractor not only refused to hand over the project documentation to the customer but did not even complete its development. Additionally, the contractor failed to deliver part of the equipment purchased with funding from the Eastern Europe Energy Efficiency and Environment Partnership (E5P) Fund.

The Polish company also refused to carry out certain previously agreed works and blocked access for another contractor responsible for connecting the complex to the external power grid.

Following the notice of termination, the contract will come into force in 14 days. These conditions are stipulated in the agreement.

The administration promises to provide separate notification regarding when the Lviv solid waste processing plant will be completed and put into operation. EcoPolitic reminds readers that the plant’s construction deadlines have been continually postponed. In April 2023, the Mayor of Lviv Andriy Sadovyi announced that the waste processing complex would be completed by the end of the year. At the beginning of July that year, completion stood at 37.7%, and by August 2024 it had reached 65%.

By September 2024, construction was halted due to contractor violations; however, in November, new promises were made – to commission the plant and complete all commissioning work by August 30, 2025.

Related
Up to €500,000 for destroying food: Spain is taking drastic measures to combat waste
Up to €500,000 for destroying food: Spain is taking drastic measures to combat waste

The maximum fine applies to repeat offenses, including the intentional destruction of food products

How to celebrate Easter without harming the environment: simple tips
How to celebrate Easter without harming the environment: simple tips

The key is to be mindful of your consumption and avoid single-use items

The global waste management crisis: humanity is eight years ahead of projections
The global waste management crisis: humanity is eight years ahead of projections

Globally, only 21% of waste is recycled, while 30% is simply dumped in open areas or not collected at all

A company known for a scandal in Lviv may build a waste processing plant in Khmelnytskyi
A company known for a scandal in Lviv may build a waste processing plant in Khmelnytskyi

Control Process S.A. had previously been involved in a number of disputes in its home country of Poland