Cardboard factory in Zhytomyr region reduces energy consumption by 20%

Cardboard factory in Zhytomyr region reduces energy consumption by 20% zhitomir.info

Maria Semenova

Production processes now require 65,000 GJ less thermal energy

The Zhytomyr Cardboard Factory has completed energy modernization work on one of its workshops. The project was implemented thanks to co-financing from the German Society for International Cooperation (GIZ).

This was reported by Zhytomyr.info.

Results in numbers

The project to improve the energy efficiency of production was implemented with joint funding: 20% from GIZ, over 30% from bank loans, and about 50% from the company's own funds.

Thanks to the work carried out, the cardboard factory managed to reduce its energy costs by 18%. Overall, the production process now requires significantly less thermal energy – 65,000 GJ.

“If we look at the results, everything was completed in full and on time. I believe this is truly remarkable, considering all the circumstances – power outages, workforce issues – yet it was still possible to accomplish and implement on schedule,” noted GIZ “BAT for Ukraine” project director Gabriel Sauer.

Comprehensive effect

The project increased production energy savings, while also reducing its negative environmental impact through indirect emissions. At the same time, the savings on energy costs allow for a reduction in the production cost of cardboard and paper products.

“This is a vivid example of how you can combine and achieve environmental results – reducing emissions, improving the environmental profile of the region, and gaining an economic effect,” emphasized Ministry of Economy of Ukraine representative Bohdan Semenenko.

Previously, EcoPolitic reported how the mining and metallurgical company Ferrexpo is modernizing its production.

The Ministry of Economy has presented the “Green Platform” for business – an online hub to search for sustainable development project financing.

The state will also compensate businesses for the interest rate on “green” loans aimed at implementing energy-efficient measures.

Related
Ukraine's first waste-to-energy plant may be shut down due to the Zhytomyr City Council
Ukraine's first waste-to-energy plant may be shut down due to the Zhytomyr City Council

Despite rising costs across the board, the city does not want to revise the rates

The cause of the mass fish kill in Zhytomyr Oblast has been identified
The cause of the mass fish kill in Zhytomyr Oblast has been identified

The death of river animals due to water contamination caused damage amounting to over 2 million hryvnias

YASNO explained how many years it takes for a solar power plant to pay for itself for businesses
YASNO explained how many years it takes for a solar power plant to pay for itself for businesses

The bureaucratic aspects of setting up a SES are becoming more standardized

The EU is allocating an additional €2.7 billion for industrial decarbonization projects
The EU is allocating an additional €2.7 billion for industrial decarbonization projects

Implementation of these projects will reduce emissions by 210 million tons of CO2 over the first ten years